Project Specification

Project Size - 320,000 sq ft

Tolerance achieved - FM2

Demolition, Design & Installation - Less than 3 months


Alongside our Middle Eastern partner, DAC, we were proud to undertake the full package on this project at the end of 2020.

CBS undertook to demolish and remove the existing slab, and then designed and built the new fibrous floor with a dry shake finish. The project took less than 3 months to take out and replace the whole floor, including the dock levelers, all in-house as one contract.



Project Summary