Project Specification

Concrete Pour Size - 601,761 sq ft

Tolerance achieved - FM1

Concrete Laid per day - 420㎥, 2200m²


Our team recently finished working on a new warehouse in Doncaster which was over 600,000 sq ft. Due to the nature and purpose of the warehouse, the concrete was laser poured to FM1 tolerance. All completed by our experienced and talented in-house labour team.


“CBS were fantastic - they delivered not only to a tight schedule but also to the highest quality and on budget."

Project Summary