Project Specification

Concrete Pour Size 7,600 ㎡

Tolerance achieved FM2

Concrete Laid per day 200 ㎡


Our team installed concrete flooring for an external yard at an independent petrol station in Leicester for our clients Tokheim PLC.


We installed 600m2 concrete laid in bays with permanent K-Form formwork and sealed joints with an oil resistant sealant.


We used an external yard brush finish and completed the project in just 1 week.


“CBS installed our concrete yard 1 month ahead of schedule"